Burriana City Council and FACSA improve public utilities in the Burriana maritime area

facsa-burriana-network-renewal
  • Work continues on the renovation of the water supply and sewage network in the municipality
  • A total of 2,5 km of the water supply network and more than 500 m of the sewerage network have been renewed.

The plan for the Renewal and Improvement Works of the Drinking Water Supply and Sewerage Infrastructure of Burriana for 2020 is progressing well and as planned, as has been verified by the Councilor of Services of the Burriana City Council, Vicente Aparisi, who, together with various representatives of the concessionary company FACSA, have visited some of the points of action contemplated in the Plan this week.

Initially, the work has moved to Pescadores Street, in the town's seaside district, where the entire water supply and sewage network is being renovated, and the street is being repaved across its entire width. This renovation work complements the work already completed this year on Rosa dels Vents and Formentera Streets, as well as the installation of a new sewage system to serve the beach bars on Arenal Beach.

This work will conclude with the renovation of the drinking water network on calle Illes Balears, calle la Farola and avenida Mediterránea, continuing the project to improve the seafront area that began a few years ago with the supply works on calle Camí del Grau, Malva-rosa, Avenida Mediterránea and Amistat, where the works were also used to renew the pavements.

In total, 2,5 km of the water supply network have been renewed, with high-density polyethylene pipes with diameters between 75 and 200 mm, and more than 500 m of the sewerage network.

Similarly, representatives of the entities have visited the site of the renovation works of the supply network of the Vila-real road, where the opportunity has also been taken to adapt the sidewalks, as well as those carried out in the sewer network of some of the main streets of the municipality: Rosa dels Vents, Formentera, Plaza Mercé, Bisbe Lluis Pérez, Cardenal Cisneros, Oviedo, Padre Villalonga, Maestro Falla, Avenida Nules and Hortolans.

Furthermore, over the past few weeks the improvement project has progressed in the city center, specifically on Divina Pastora Street and in the Plaza Mayor, where in addition to renewing the network in some streets, the renovation of the pavement is planned, with natural stone in the case of Divina Pastora Street.

All these works, which represent an investment of around 1.083.353,74 euros, are part of the intervention plan launched by the City Council and FACSA to improve the quality and guarantee of water supply, as well as to improve pedestrian mobility and the safety of public roads since, although the priority is the renewal of the network, the council has considered it appropriate to take advantage of these works to adapt the sidewalks.

Need help?

We are here for whatever you need

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.