21 April 2022
Obremo builds the Sancho Llop electrical substation in Gandía (València)
The team from the Electricity area of Obremo is carrying out the civil works for the construction of the new 220/20KV Sancho Llop electrical substation in Gandía for I-DE Redes Eléctricas inteligentes, SA (Iberdrola Distribución, SA).
The project is a comprehensive one that covers tasks such as earthworks, general earthing grid, interior and exterior drainage, foundations for gantries and equipment supports, electrical ducting, transformer beds, foundations, slabs, interior and exterior roads, partial fencing of the site with metal railings, among other technical operations.
The works, which began in June 2021, were halted until last December because of the discovery of archaeological remains. Completion of the project is scheduled for July 2022 with an approximate budget of 1.2 million €.
Since 2002, Obremo Electricity has specialised in LV, MV and HV work for the construction of Underground Networks, Overhead Lines, Transformer Stations (TS) and Electrical Substations for distribution companies, photovoltaic plants and private individuals alike. These operations cover civil works and electrical assembly, as well as subsequent maintenance.
Related news
Need help?
We are here for whatever you need