15 January 2025
Obremo completes the construction of the new Cascajos Distribution Substation in Logroño: a boost to energy efficiency
The Electricity Area of Obremo 's Electricity Area has successfully completed the construction of the new Cascajos 66/13kV Distribution Substation (STR) in Logroño, a strategic project that has strengthened the region's electrical infrastructure and ensured a more efficient and reliable distribution of energy.
The new facility, which features a semi-underground main building, has been designed to house the necessary 66 kV and 13,8 kV systems and equipment. The work carried out by the Obremo team included earthworks, pile driving for the diaphragm wall, construction of the semi-underground building, and the final finishing of the structure.
The project, developed over a period of 10 months, has stood out not only for its technical complexity, but also for the efficiency in the management of time and resources used.
It is worth noting that the Cascajos Distribution Substation will contribute significantly to the improvement of the local electricity network, guaranteeing a more stable supply and prepared to respond to future energy demands.
With this initiative, Obremo reaffirms its commitment to innovation and excellence in the development of key infrastructures, essential for sustainable progress.