12 January 2023
Obremo begins construction of a new distribution substation in Logroño to improve the city's electricity supply
Obremo has begun the civil engineering work for the construction of the new Distribution Substation (STR), which will improve the electricity supply for residents of the urban area of the city of Logroño, La Rioja.
The execution of this operation, which will last approximately ten months, includes the construction of diaphragm walls and the installation of the decorative cladding for this new substation. In recent weeks, the team of specialists from Obremo 's Electrical division has begun excavating the site where the semi-underground main building will be located, which will house the power transformers with 66 kV and 13.8 kV systems.
To date, the team has also completed a 20-meter horizontal directional drilling (mole) to connect to the STR stormwater drainage system, as well as the guide walls in preparation for the construction of the diaphragm walls. Once the building construction is finished, the main facade will be completed, giving the building a distinctive architectural appearance.
For this purpose, there is currently a team of eight people and two rotating machines, which will be considerably increased when the diaphragm walls are started.
This award of I-DE by Iberdrola has meant the expansion of the geographical area where Obremo Electricidad carries out its activity, adding new autonomous communities to the historical ones for the company such as Comunitat Valenciana, Euskadi and Region of Murcia.