Foz promotes a strategic modernization of its urban water cycle with a new management contract

The Electricity Area team of Obremo It carries out the civil engineering work for the construction of the new 220/20KV Sancho Llop electrical substation in Gandía for I-DE Redes Eléctricas Inteligentes, SA (Iberdrola Distribución, SA).
The work is a comprehensive project that includes tasks such as earthworks, general grounding grid, interior and exterior drainage, foundations for portals and equipment supports, electrical conduits, transformer bases, foundations, slabs, interior and exterior roads, partial enclosure of the work with metal fencing, among other technical operations.
Work, which began in June 2021, was halted until last December due to the discovery of archaeological finds. The project is scheduled for completion in July 2022 with an approximate budget of €1.2 million.
Since 2002, Obremo Electricidad specializes in low, medium, and high voltage electrical work for the construction of underground networks, overhead lines, transformer substations, and electrical substations for distribution companies, photovoltaic plants, and private individuals. These operations encompass civil works, electrical installation, and subsequent maintenance.