3 November 2020
UBE commissions Gimecons to expand its materials warehouse in Castelló
UBE, a multinational company dedicated to the production and distribution of chemical products, has entrusted Gimecons with the civil works and metal structures of the expansion project of the materials warehouse that it has at its plant in Castelló.
The work will be carried out in three phases. The first phase, which began last September, involves demolishing the shed and the existing open-air storage area for materials. The second phase focuses on expanding the warehouse itself using hot-dip galvanized steel structural profiles. It will also include a new sheet metal roof covering almost 1.000 square meters on its west and east sides.
Finally, Gimecons will proceed with the construction of a small spare parts warehouse and offices using a 242 m² intermediate floor slab made of hollow-core slabs and a new canopy in the east area. These works will be completed next March after 24 weeks of construction.